Barron Park Elementary School

ELEMENT DESCRIPTION PROJECT COST
1 DEMOLISH EXISTING ADMIN AND MULTI‐PURPOSE. CONSTRUCT NEW WING WITH ADMIN, LEARNING CENTER, MP AN DENRICHMENT LAB. $10,387,356
2 DEMOLISH KINDER WING AND ADD THREE NEW CLASSROOMS WITH NEW PLAY STRUCTURE AND COVERED EATING AREA. $6,163,237
3 REMOVE PORTABLES AND CONSTRUCT NEW WING WITH CLASSROOM AND TWO ENRICHMENT LABS. $2,818,938
4 EXISTING CLASSROOM UPGRADE THROUGHOUT WITH A/C AND ENVELOPE UPGRADES. CONVERT TWO EXISTING CLASSROOMS INTO ENRICHMENT LABS. $5,988,230
5 NEW SOLAR (PV) SYSTEM. $935,011
6 NEW ACCESSIBLE PLAYGROUND. $1,084,448
    $27,377,218