1 |
NEW KINDER CLASSROOM WING WITH PLAY AREA. CONVERT EXISTING KINDER INTO THREE ENRICHMENT CLASSROOMS. |
$11,843,787 |
2 |
CONSTRUCT FIVE NEW CLASSROOMS, LEARNING CENTER AND RESOURCE CENTER. DEMOLISH PORTABLES. LIFE SAFETY AND ADA UPGRADES REQUIRED. |
$14,787,540 |
3 |
RENOVATE INTERIOR OF MULTIPURPOSE ROOM AND CONVERT FLEX AREA INTO SERVERY. |
$2,455,201 |
4 |
EXISTING CLASSROOM UPGRADE THROUGHOUT WITH A/C AND ENVELOPE UPGRADES. |
$3,329,300 |
5 |
SITE UPGRADES TO INCLUDE ACCESSIBLE RAMP DOWN TO PLAYGROUND AND PROVIDE COVERED EATING AREA. |
$167,227 |
6 |
NEW SOLAR (PV) SYSTEM. |
1,233,721 |
7 |
NEW ACCESSIBLE PLAYGROUND. |
$1,430,898 |
|
|
$35,247,674 |