ELEMENT DESCRIPTION PROJECT COST
1 Strong Schools Bond: Construct new MP & Enrichment Lab. Convert existing MP to two classrooms. Construct additional kinder class.                        S.S.B.
2 Demolish existing Admin and MP. Construct new Admin, Library, Enrichment Lab and Resource Center. $11,006,691
3 Demolish Library and Portables. Construct new classroom wing with learning center. Construct two additional new classrooms and add space to create new kinder class. $19,434,567
4 Existing classroom upgrade throughout with a/c and envelope upgrades. $7,481,034
5 New solar (pv) system. $2,056,201
6 New accessible playground. $1,430,898
    $41,409,391