Henry M. Gunn High School
Element | Description | Project Cost |
---|---|---|
1 | MAJOR MODERNIZATION OF BUILDINGS A & B FOR ADMIN AND FOOD SERVICES | $13,711,277 |
2 | DEMO BUILDING M AND BUILD NEW MEDIA ARTS / ARTS BUILDING | $21,825,883 |
3 | BUILD ADDITION TO TITAN GYM, ADD AC TO GYM AND NEW CONCESSIONS BY STADIUM | $11,097,639 |
4 | MAJOR MODERNIZATION OF BOW GYM, WITH NEW LOCKER/SHOWER/RESTROOM AREA | $13,270,440 |
5 | MAJOR MODERNIZATION OF SPANGENBERG THEATER | $20,449,097 |
6 | RE‐PROGRAM SCIENCE OFFICE AREA INTO TWO NEW LABS AND BUILD ADDITION FOR OFFICES | $11,315,758 |
7 | MAJOR MODERNIZATION AND ADDITION FOR BUILDING L FOR CTE LABS | $14,115,908 |
8 | MINOR MODERNIZATION OF BUILDINGS C, D, E, F & G | $11,032,979 |
9 | FOOTBALL STADIUM IMPROVEMENTS | $6,297,206 |
10 | SOCCER AND BASEBALL STADIUM IMPROVEMENTS, INCLUDING LIGHTING AND NEW SOCCER FIELD TURF | $4,552,511 |
11 | NEW PARKING LOT CONFIGURATION AND SOLAR (PV) PANELS | $9,090,508 |
$136,759,206 |